Current Dev Position: YP 2.7 M1.

Next Deadline: YP 2.7 M1 Cutoff is Dec. 10, 2018


SWAT Team Rotation:

· SWAT lead is currently: Paul

· SWAT team rotation: Paul -> Ross on Nov. 23, 2018

· SWAT team rotation: Ross -> Amanda on Nov. 30, 2018

· https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

· YP 2.6 (thud) was released based on rc1.

· We’d like to thank everyone who was involved in 2.6 for making what is shaping up to be a great project release. This applied to everyone involved, be it through patches, docs, bug triage, autobuilder, QA, programme management, bug reporting, sysadmin or anything else, it all goes to helping the releases (and hence the project) being successful.

· YP 2.4.4 (Rocko) is in QA and 93% complete. See: https://wiki.yoctoproject.org/wiki/2.4_QA_Status

· Master has opened for new changes for 2.7 M1 and patches are being tested and merged as usual.

· The next release will be ‘warrior’ followed by ‘zeus’.

· The AUH has sent out patches for various upgrades recently which is timely for merging into 2.7 so lets collect those up and get them merged!

· There are some autobuilder changes happening at the moment to assist us with the QA changes happening in 2.7. We updated to the recent buildbot 1.6.0 release which contained bug fixes for some UI glitches we were seeing (was good to be able to work with the latest code!).


Planned Releases for YP 2.7:

· YP 2.7 M1 Cutoff is Dec. 10, 2018

· YP 2.7 M1 Release Target is Dec. 21, 2018

· YP 2.7 M2 Cutoff is Jan. 21, 2019

· YP 2.7 M2 Release Target is Feb. 1, 2019

· YP 2.7 M3 Cutoff is Feb. 25, 2019

· YP 2.7 M3 Release Target is Mar. 8, 2019

· YP 2.7 M4 Cutoff is Apr. 1, 2019

· YP 2.7 M4 Release Target is Apr. 26, 2019


Planned upcoming dot releases:

· YP 2.4.4 (Rocko) is in QA. See: https://wiki.yoctoproject.org/wiki/2.4_QA_Status

· YP 2.5.2 (Sumo) will be targeted after YP 2.4.4 is done.

· YP 2.6.1 (Thud) will be targeted after YP 2.7 M1 is done.

· YP 2.5.3 (Sumo) will be targeted after YP 2.7 M4 is done.

· YP 2.6.2 (Thud) will be targeted after YP 2.5.3 is done.


Tracking Metrics:

· WDD 2418 (last week 2402) (https://wiki.yoctoproject.org/charts/combo.html)

· Poky Patch Metrics

o Total patches found: 1711 (last week 1716)

o Percentage of patches in the Pending State: 738 (43%) [last week 739 (43%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features


The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager