Current Dev Position: YP 2.7 M1.

Next Deadline: YP 2.7 M1 Cutoff is Dec. 10, 2018


SWAT Team Rotation:

· SWAT lead is currently: Amanda

· SWAT team rotation: Amanda -> Chen on Dec. 7, 2018

· SWAT team rotation: Chen -> Arminon Dec. 14, 2018

· https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

· YP 2.4.4 was released

· Some progress has been made on fixing the oe-selftest stability issues reported last week. As an idea of scale there have been over 20 different issues found so far but others continue to appear.

· Patches are merging to master but at a reduced rate due to the selftest stability problem.

· Please be aware 2.7 M1 is due to be built on Monday.


Planned Releases for YP 2.7:

· YP 2.7 M1 Cutoff is Dec. 10, 2018

· YP 2.7 M1 Release Target is Dec. 21, 2018

· YP 2.7 M2 Cutoff is Jan. 21, 2019

· YP 2.7 M2 Release Target is Feb. 1, 2019

· YP 2.7 M3 Cutoff is Feb. 25, 2019

· YP 2.7 M3 Release Target is Mar. 8, 2019

· YP 2.7 M4 Cutoff is Apr. 1, 2019

· YP 2.7 M4 Release Target is Apr. 26, 2019


Planned upcoming dot releases:

· YP 2.5.2 (Sumo) will be built soon.

· YP 2.6.1 (Thud) will be targeted after YP 2.7 M1 is done.

· YP 2.5.3 (Sumo) will be targeted after YP 2.7 M4 is done.

· YP 2.6.2 (Thud) will be targeted after YP 2.5.3 is done.


Tracking Metrics:

· WDD 2425 (last week 2426) (https://wiki.yoctoproject.org/charts/combo.html)

· Poky Patch Metrics

o Total patches found: 1675 (last week 1682)

o Percentage of patches in the Pending State: 736 (44%) [last week 734 (44%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features


The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley